Oil & Gas · North Sea, United Kingdom · 2025

Three compressor overhauls in eighteen months traced to sub-micron aerosol carryover that the existing knock-out drum could never have removed.

Measured carryover after commissioning
0.08 ppmw
Compressor overhauls in 20 months since
0
Installation inside planned shutdown
11 days
Payback against deferred production
7 months

The challenge

The platform had suffered three unplanned compressor overhauls in eighteen months, each costing several weeks of deferred production. The operator suspected element quality. Sampling showed something else entirely: the existing vessel was a gravity knock-out drum being asked to remove aerosols below 3 µm — a duty no gravity separator can perform at any element quality.

How we approached it

  1. 01Isokinetic sampling at the compressor suction quantified actual carryover at 42 ppmw against a specification of 0.5 ppmw.
  2. 02Gas density was recalculated at true operating conditions, revealing the existing vessel was running at 2.3 times the critical Souders-Brown velocity.
  3. 03A two-stage coalescer was sized for the correct velocity, then modelled in CFD to confirm drainage back to the sump at minimum turndown.
  4. 04Deck loading and available footprint were verified against the platform structural drawings before fabrication released.

What we delivered

A SEPRA-C vertical coalescer in duplex 2205, sized to hold gas velocity at 0.6 times the Souders-Brown critical value across the full turndown range, with a two-stage element set and an instrumented liquid sump discharging to the closed drain header. Installed inside an eleven-day shutdown window.

The diagnosis was the valuable part. We had been replacing elements for a year and a half in a vessel that was never going to work. They told us that in the first meeting, with the numbers to back it.
Rotating Equipment Lead · North Sea operator

Project facts

Client
Confidential — North Sea operator
Industry
Oil & Gas
Location
North Sea, United Kingdom
Year
2025

Measured results

0.08 ppmw
Measured carryover after commissioning
0
Compressor overhauls in 20 months since
11 days
Installation inside planned shutdown
7 months
Payback against deferred production