Cement & Building Materials · Rajasthan, India · 2024

A tightened national emission limit gave an operating kiln eleven months to reach a standard its existing electrostatic precipitator could not meet.

Measured stack emission
3.8 mg/Nm³
Conversion completed in outage
17 days
Compressed air saving vs. timer cleaning
48%
Capital saved by reusing casing
62%

The challenge

A revised emission standard cut the permitted limit from 50 to 30 mg/Nm³, with a further reduction announced for the following cycle. The existing ESP averaged 34 mg/Nm³ and could not be economically uprated. The kiln could not stop outside its planned annual outage of nineteen days.

How we approached it

  1. 01Gas composition, temperature profile and acid dew point were measured across a full production cycle including kiln upsets.
  2. 02The conversion was designed to reuse the existing ESP casing, cutting both cost and installation time substantially.
  3. 03PTFE membrane media was selected to deliver headroom against the announced future limit rather than only the current one.
  4. 04Erection sequencing was planned hour by hour against the nineteen-day outage, with pre-assembled modules staged on site beforehand.

What we delivered

Conversion of the existing precipitator casing to a CYCLA-BH pulse-jet baghouse with PTFE membrane bags, on-demand differential-pressure cleaning, and full explosion protection designed to the measured Kst of the kiln dust. Completed within the outage with two days to spare.

They planned the outage in hours, not days. The modules arrived pre-assembled and we restarted two days early — that had never happened on this site.
Plant Head · Integrated cement producer

Project facts

Client
Integrated cement producer
Industry
Cement & Building Materials
Location
Rajasthan, India
Year
2024

Measured results

3.8 mg/Nm³
Measured stack emission
17 days
Conversion completed in outage
48%
Compressed air saving vs. timer cleaning
62%
Capital saved by reusing casing